Groundworks

  • Client

    Taylor Woodrow

  • Location

    Hagley, Birmingham

  • Project Value

    £500,000

  • Duration

    16 Weeks

  • Services Provided

    Remediation, groundworks, drainage and sewers, headwall construction

Following on from the demolition and remediation of the site, VertaseFLI undertook infrastructure drainage and groundworks for a residential development scheme.  A large diameter sewer was diverted and replaced which involved over-pumping of a significant section.

Further Information

VertaseFLI acted as Principal Contractor.  Following remediation, the scheme included a major earthworks and re-profiling scheme before commencing in the construction of primary infrastructure and services, including the placing of kerbs, sub-base and base course tarmac. 
 
A large diameter culvert was also diverted and drainage connection made for both foul and surface water.